Southern Walnut Creek Trail Project
Background:
The Southern Walnut Creek Trail is a planned 7.3 mile trail along the Walnut Creek Greenbelt. The project includes the construction of bridges, trail heads, and other trail amenities. The entire trail is expected to be constructed of concrete 10' in width with two foot grass shoulders, including an expected 5 bridges, 3 culverts, signage, benches, and parking lots at trailheads. There will be two trailheads at Johnny Morris Road and one trailhead at Govalle Park.
Project Updates and Schedule:
This project will be brought before City Council next Thursday, February 2, 2012 for approval of the construction contract. It is estimated that the project will take approximately one and a half years to complete.
Click here to view the project map
Contact Us:
The project team would be happy to send email updates directly to you. Your address will remain confidential and will be used solely for the purpose of sending updates about the project.
Richard Duane, Project Manager, (512) 974-7730