Name: Linear feet of storm drain pipe installed via public-private (P3) and public-public (P4) partnership projects.
Description: The linear feet of storm drain pipe installed with construction projects managed by private developers, other City departments or external government agencies via cost-sharing participation using WPD funds. This does NOT include installation of pipeline installed by other private or public sector projects where the installation is required to meet their standard regulatory requirements associated with a development or redevelopment project. This measure does include WPD funded improvements via pie upsizing, addition of new systems for increased capacity and existing system replacement/rehabilitation due to the condition of pipelines in association with participation projects where WPD funds are used to cover the differential cost above the regulatory minimums.
Type: Output

Current Data - Annually

2021 Target 2021 Actuals
1000 0

History Data

FY 2016 Actual FY 2017 Actual FY 2018 Actual FY 2019 Actual FY 2020 Actual FY 2020 Target FY 2021 Target
2613 1365 300 460 1270 1600 1000