The City of Austin Public Works Department is currently in the process of designing the Meadow Lake Boulevard street extension project. 

In accordance with City Council Resolution No. 20160421-036, this project will add connectivity for residents in the neighborhood by extending Meadow Lake Boulevard from Misty Slope Lane to Quicksilver Boulevard. The project will include sidewalks, protected bicycle lanes and other traffic improvements to provide better access to Perez Elementary School. 
 

Map of the Meadow Lake Boulevard Extension Project area

Project Schedule 

  • Design Phase: June 2017 - May 2021
  • Bid Phase: May 2021 - Oct. 2021
  • Construction Phase: Target Oct. 2021 - Oct. 2022

Dates are projected as accurately as possible but are subject to change. 

Construction Budget

$2.5 million 

Project Highlights

  • Protected two-way bike lanes                                               
  • Installation of sidewalks 
  • Two one-way travel lanes
  • Street lighting 
  • Parallel parking
  • Water and wastewater lines
  • Storm drain
  • Detention pond

Renderings: Proposed Street Design & Site Plan

Community Engagement

Sign up for project updates (select Meadow Lake Blvd updates)

Construction Impacts

Water Shut-Outs: There will be temporary water service shut-outs that will impact five lots near the project site. The project inspector will hand out written notices to affected residents 48 hours prior to the shut-outs. The inspector will coordinate with the contractor to schedule the shut outs at the least disruptive time to the residents.

Traffic: Traffic impacts will be minimal. This project area is undeveloped and outside of the current traffic area.  Driveways will not be blocked during the project. The project team will work with the contractor to make sure construction truck traffic impact is minimized as much as possible.

Residents may notice an increase in truck traffic due to construction material delivery.  Allowable work hours will be Monday through Friday, 7 a.m. to 6 p.m. The project will comply with the City’s noise ordinance.

Project Contacts

Dario Octaviano, Project Manager
(512) 974-7607
Email

Ramiro Hernandez, Project Inspector
(512) 825-7863
Email

Matt Hart, Public Information
(512) 974-7268
Email