Westgate Neighborhood Wastewater Pipeline Renewal
Project Overview
As part of the Renewing Austin program, Austin Water is bringing improvements to the wastewater system in the Westgate neighborhood. We have documented a number of overflows in this area, and new lines will help us conserve water, improve reliability for customers, and reduce expenditures on frequently breaking lines.
The Westgate Neighborhood Wastewater Renewal Project will take place in the parts of the Williamson Creek Basin that sit in the Westgate, Franklin Park, and South Creek neighborhoods. We will rehabilitate 12,300 linear feet of wastewater lines and 1,050 linear feet of water lines. The Watershed Protection Department will rehabilitate 200 linear feet of stormwater line during this project as well.
We will partner with the City of Austin’s Capital Delivery Services (CDS) Division for the construction phase of this project, which will be managed by CDS project management staff.
Timeline
Construction is scheduled to begin in late August 2024 and take approximately 19 months to complete. Streets disturbed by construction during this project will be repaved when the entire project is complete.
Communications
Project Documents
- View Project Map Areas 1-3
- View Project Map Area 4
- View Project Map Area 5
- View Project FAQs
- Public Meeting Presentation, Sept. 18, 2024
Contact
Tony L. Lopez, P.E., Project Manager
Austin Capital Delivery Services
512-974-6581
tony.lopez@austintexas.gov
Justin Trevino, Construction Inspector
Austin Capital Delivery Services
512-905-7300
justin.trevino@austintexas.gov
Cynthia Miller, J.D.
Austin Water Public Information Office
512-972-0268
cynthia.miller@austintexas.gov