Rainey Street Permit Updates

Rainey Street Permit Updates – 12/09/2024

Below is a list of active and pending right of way permits for the area around Rainey Street as of December 9, 2024. You can note the permit number, contractor, location, permit open and close date, as well as a description of the work being done.

Contact Information for the permit holders and/or project contractors can be found by clicking on the permit number and accessing the hyperlink connecting to the Austin Build + Connect portal.

Permit Dates reflect the date range when work is allowed under the permit. Work can begin at any time within the permit window.

Work schedules and scope are subject to change and unforeseen delays due to weather, utility issues, etc. Unpermitted work in the right of way may also be present. Please contact Evelyn Powers, Right of Way (ROW) Project Coordinator, at RightOfWay@austintexas.gov or call the ROW office at 512-974-7828 if you have any further questions.

Map of Rainey Street Closures

Active Permits

Below is a list of active right of way permits as of Monday, December 9, 2024.

Bierce Street

 
Permit # Contractor Location Permit Open Date Permit Close Date Description Closure

 

Cesar Chavez Street

 
Permit # Contractor Location Permit Open Date Permit Close Date Description Closure

 

Cummings Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure

 

Davis Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
24-086126 DS Lehne Construction 610 Davis St 08/16/24 02/12/25 Installing new alley pavement, curb/gutter, and pavement sub slab Behind existing long-term alley closure between Red River Street and Rainey Street

 

East Avenue

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
24-078926 EX AE/FRI East Ave 10/21/24 3/31/25 Installing electrical duct bank along East Avenue Full closure of East Avenue from River Street to Lambie Street

 

Rainey Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
22-034116 RW Flintco 90-97 Rainey St 4/4/22 02/14/24 Long-term closure for duration of project Sidewalk / parking on north side of Davis Street, Rainey Street metered parking & sidewalk (west curb) just north of Davis Street intersection
22-167152 RW JE Dunn 80 Rainey St 1/10/23 12/30/24 Long-term sidewalk and bike lane closure for duration of 48-story tower project Rainey Street sidewalk (west side) and parking closed on both sides to maintain two-way vehicular traffic

23-022904 RW

 

Ironwood/Trine 91 Rainey St 6/28/23 12/2/24 Repair to building at southwest corner of property None (covered pedestrian walkway provided)

24-095662 DS

 

Lehne Construction 92 Rainey St 08/16/24 02/12/25 Installing new alley paving, curb/gutter, and paver sub slab Behind existing long-term closure
24-148727 RW JE Dunn / Austin Crane 60-89 Rainey St 01/03/25 01/10/25 Tower crane dismantling Full closure of Rainey Street from Davis Street to River Street; sidewalk to remain accessible
24-128084 RW Flintco / Lewis Crane 90 block Rainey St 12/04/24 12/24/24 Tower crane dismantling Full closure of Rainey Street

 

Driskill Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
2024-106019 RW Grande / R&S 600 block Driskill St 10/03/24 01/12/25 Fiber splicing Street narrows

 

Red River Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
22-006772 RW DPR Construction 98 Red River St 5/28/22 05/11/25 Long-term travel lane and sidewalk closure for duration of project Travel lane and sidewalk closure on south side of Cesar Chavez Street and west side of Red River Street; east sidewalk on Red River Street closed to maintain two-way vehicular traffic

24-070619 DS

 

Vesta 98 Red River St 06/14/24 12/11/24 Install sidewalk, curb & gutter Behind existing closure on Red River Street

22-120570 DS

 

Vesta 98 Red River St 06/14/24 12/11/24 Install four driveway approaches Behind existing closure on Red River Street

 

River Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
22-010435 RW DPR Construction 700 River St (North side of the street) 7/6/2022 12/13/24 Long-term traffic control setup for 43-story residential project Parking lane and sidewalk closure on north curb of River Street between Rainey Street and East Avenue
23-124393 DS SLC Services 700 River St 10/24/23 06/08/25 Installing sidewalk, curb and gutter Behind the 700 River Street closure (mentioned above)

 

Pending Permits

The list below includes new permits that are under review, or subject to potential extension.

Bierce Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure

 

Cummings Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
23-136205 EX GFT / BCOMM 700 block Cummings St     Vault install Alley closure
23-079476 RW GFT / B. Robinson 700 block Cummings St     Installing aerial fiber Travel lane and sidewalk closure on north curb

 

Davis Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure

 

Driskill Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
24-061517 EX TGS 700 Block Driskill St Replacing gas main Sidewalk closure

 

East Avenue

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
24-153307 RW DPR Construction 62 East Ave     Dumpster placement  

 

Rainey Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure

 

Red River Street

Permit # Contractor Location Permit Open Date Permit Close Date Description Closure
24-129926 RW Vertex 91 Red River St     Window cleaning Sidewalk closure

 

River Street

 
Permit # Contractor Location Permit Open Date Permit Close Date Description Closure

 

Additional information on private development with ROW work in the area can be found in the Development Tracker and Property Profile tools, linked below.