Sign-up for email updates
Project Updates
Background
The City of Austin Parks and Recreation Department is excited to partner with Austin Parks Foundation to renovate the Montopolis Neighborhood Park playground. Engagement for the Montopolis Pool Project highlighted the need for improved drainage and updated amenities at the playground. Austin Parks Foundation led efforts for engagement and planning for the updated play area.
Project Description
Austin Parks Foundation led the playground project, aiming to include new play equipment, play surfacing, improved drainage, concrete walks, seating, shade, and nature play elements.
Anticipated Timeline
The playground construction will occur at the same time as the pool renovations.
- Concept Design and Community Engagement: Fall 2023 (completed)
- Permitting: Winter 2023 to Fall 2024 (completed)
- Construction: December 2024 to Summer 2026
- Anticipated completion: Summer 2026
Community Engagement
Several pop-up and community events were held in the fall and winter of 2023. The community feedback is shared below.
- Playground Pop Up at Allison Elementary School
December 13, 2023 from 2:45 to 3:30 p.m.
515 Vargas Road, Austin, Texas 78741
- Playground Pop-Up at Montopolis Holiday Cheer Event
December 9, 2023 from 11 to 1:30 p.m.
Montopolis Recreation and Community Center
1200 Montopolis Dr., Austin, TX 78741
- Playground Pop-Up
November 8, 2023 from 4:30 - 6:30 p.m.
Montopolis Recreation and Community Center
1200 Montopolis Dr., Austin, TX 78741
- Community Survey #1: Closed Fall 2023
- Staff Feedback Questionnaire
Contact Information
For more information, please contact Patrick Beyer, PARD Project Manager, by email or phone at (512) 974-9476.