Project Overview
The West Riverside Reclaimed Water Main is part of a series of projects that will provide redundancy and reliability of service to reclaimed water customers in Austin.
The project includes installation of approximately 2,800 feet of 24-inch pipeline from S 1st St to Lee Barton Dr. It will be installed mostly by conventional open trench, but about 650 feet will be installed via Horizontal Directional Drilling. The project will facilitate further expansion of the reclaimed system. Potential service connections to the new reclaimed water main includes Town Lake Metro Park at Auditorium Shores.
Timeline
- Advertise/Bid/Award: Fall 2025 – Winter 2025
- Active Construction: Spring 2026 – Fall 2027
Project Documents
Contact
James Mendez, Project Manager
Capital Delivery Services, City of Austin
james.mendez@austintexas.gov
512-974-3662
Emlea Chanslor, Community Outreach
Public Information Office, Austin Water
emlea.chanslor@austintexas.gov
512-972-0145